Category: News
Entries that appear on the news page.
Rugged Robbins TBM and Conveyors go for Gold in Indianapolis
The News In Brief:
- The Robbins 6.2 m (20.2ft) diameter Main Beam TBM completed the Eagle Creek extension tunnel on March 5, 2015.
- The world-record-setting jobsite includes a number of unique aspects, the conveyor system being one of them. The Robbins continuous conveyor consists of 82,000 ft of belt and travels through two unprecedented 90-degree curves.
- The project was put in place to reduce the amount of raw sewage overflows in the city’s neighborhoods and clean up tributaries along the White River.
On March 5, 2015, a Robbins 6.2 m (20.2 ft) diameter Main Beam TBM finished boring a 2.8 km (9,175 ft) long extension tunnel, known as the Eagle Creek Tunnel, for the Indianapolis Deep Tunnel System in Indiana, USA. The contractor, Shea/Kiewit (S-K) JV, had much to celebrate: “I’m proud of our world records, and most of all our men and the hard work they have done as a team, working together to accomplish a project of this size,” explained Stuart Lipofsky, Project Manager, for S-K JV. “We finished the first 12.5 km (41,000 ft) [of the main tunnel] almost a year ahead of schedule. The extension added time but what is remarkable is that we were still able to finish within the original contractual dates,” continued Lipofsky. The completion of the first leg of a much larger tunnel system targets three critical CSOs that flow into the nearby White River, and will go online in 2017. The completed tunnels bring the city one step closer to achieving its consent decree with the U.S. Environmental Protection Agency (EPA), set to be achieved by 2025, to eliminate overflows into the city’s rivers.
The rebuilt Robbins hard rock TBM was first used on the 12.5 km (7.8 mi) long main tunnel, called the Deep Rock Tunnel Connector (DRTC). The new cutterhead arrived onsite in November 2012, and the machine was launched from a 76 m (250 ft) deep shaft to bore through limestone and dolomite. The TBM achieved world records in its size class of 6 to 7 m (20 to 23 ft), including “Most Feet Mined in One Day” (124.9 m/409.8 ft); “Most Feet Mined in One Week” (515.1 m/1,690 ft); and “Most Feet Mined in One Month” (1,754 m/5,755 ft). According to Tim Shutters, Construction Supervisor for project owner Citizens Energy Group, there were two main factors for the TBM’s high performance: “The first one is the very nice cutterhead provided by Robbins. It has performed very well. [Second], rock conditions are favorable for mining operations and optimal for fast production.”
Another important element that helped the speedy machine achieve a fast advance was, as Lipofsky put it, “one of the most complex continuous conveyor systems in North American tunneling construction.” The custom-built Robbins system, consisting of 25 km (82,000 ft) of belt, included horizontal and vertical conveyors for efficient muck removal. The system was the first built by Robbins to go through such sharp curves: “The belt is going through two 90-degree curves in opposite directions and S-curves in other places. It’s very unusual and amazing to see a belt system perform as well as this one did,” said Lipofsky.
Once complete, the deep tunnel project will reduce the amount of raw sewage overflows and clean up tributaries along the White River. Tim Shutters describes the environmental benefits the project will provide the Indianapolis community: “I’ve lived in Indy all of my life, and the White River has never been a focal point for the city as there is a lot of pollution. I really think that once it has been cleaned up, people will want to visit, they will swim and fish, and property values along that body of water will go up. Being able to finally utilize the river is key for us.”
After the early completion of the Eagle Creek Tunnel, the project will be moving into its next two tunneling phases. The White River Deep Tunnel will continue 8.5 km (5.3 mi) north of the completed DRTC and pump station. The Lower Pogues Run Deep Tunnel will split off 2.7 km (1.7 mi) from the White River Deep Tunnel heading east. Two additional tunnels, including Fall Creek and Pleasant Run, are anticipated to be built in 2020, and the project (27 km/17mi of tunnels in total) is expected to be fully completed by the end of 2025.
Announcing the Crossover Series of Robbins Dual Mode TBMs
Robbins proudly announces its Crossover Series of TBMs, a line of field-tested, rugged Dual Mode-type machines. Crossover TBMs feature aspects of two TBM types, and are ideal for mixed ground conditions that might otherwise require multiple tunneling machines. The XRE (standing for Crossover Rock /EPB) is the most common type of hybrid machine, and features characteristics of Single Shield Hard Rock machines and EPBs for efficient excavation in mixed soils with rock.
An XRE TBM recently completed tunneling at Australia’s Grosvenor Decline Tunnel, where it excavated two mine access drives at rates fourteen times faster than a traditional roadheader. The latest drive was completed on February 9, 2015. “This was a big step forward for the mine to appropriately use civil tunneling technology for a mining application. I take my hat off to the management of owner Anglo American Coal to have the foresight and leadership ability to take this step. Using the Crossover technology [versus the traditionally-used roadheader method], the project was finished on schedule,” said Lok Home, Robbins President.
Additional types of Crossover machines include the XSE (Crossover between Slurry/EPB) and the XRS (Crossover between Rock/Slurry) TBMs. The Crossover series is quickly gaining in popularity, with Robbins Crossover TBMs currently being assembled in Mexico, Turkey, and Azerbaijan. An XRE TBM will begin excavation for Mexico’s Túnel Emisor Poniente II (TEP II) later this year, while an XSE is being readied for excavation at the Baku Metro.
The rebranding and Crossover terminology embodies the concept that the machines are able to cross over between modes, says Home. The unique machines are a top focus point for the company: “Robbins comes at this business with extensive rock experience so everything we design comes with the assumption that there will be tough conditions. When you have to “cross over” to another mode then already you are in difficult conditions, and contractors need robust machines to get through these challenges,” says Home.
Home foresees that machine sales will grow as more projects worldwide are planned in difficult and varying ground conditions. Survey results back up the trend, indicating an increased interest in Crossover-type machines worldwide. “This is a continuous evolution and we are consistently endeavoring to improve Crossover designs. We have three of the machines in production now and I see this number increasing year by year as the industry sees and accepts their value.”
Breakthrough Robbins "Crossover" Machine Breaks Through
The News in Brief:
- The Grosvenor Decline tunnel marks the first method of a TBM being used in a coal mine in Queensland.
- The unique Crossover Rock/EPB TBM features design aspects from both hard rock Single Shield and soft ground EPB TBMs to bore through a variety of ground.
- The “Crossover” designation is new for Robbins, and will going forward be the designation for all types of Dual Mode TBMs.
- The Crossover TBM for Grosvenor was uniquely designed for excavation in conditions that included the potential for methane gas. It was designed as Class 1, Division 2 Coal Mine Compliant.
- The TBM excavated at rates fourteen times that of a traditional roadheader operation (70 m per week on average vs. 5 m per week).
- The TBM broke through into an active section of the coal mine on February 9, 2015, completing excavation of two mine access tunnels.
Full Press Release:
A ground-breaking TBM brought a mining operation one step closer to first coal on February 9, 2015. The Robbins Dual Mode “Crossover” Rock/EPB TBM completed tunneling at Anglo American’s Grosvenor Project in Queensland, Australia. The “Crossover” designation is new for Robbins Dual Mode TBMs, and will be used for all such projects going forward. The efficient type of TBM used at Grosvenor is now known as an XRE, standing for Crossover between Rock/EPB. Other types of machines are designated the XSE (Crossover between Slurry/EPB) and the XRS (Crossover between Rock/Slurry).
The Grosvenor Mine, a Greenfield coal operation, was the first to utilize TBM technology for mining tunnels in Queensland. Mine owner Anglo American Coal chose the 8.0 m (26.2 ft) machine for two decline access tunnels at grades of 1:6 and 1:8, one for conveyors and another for people and equipment.
The XRE TBM was picked over the traditionally-used roadheader method for several reasons, including excavation speed and tunnel maintenance. The choice proved prescient with the machine excavating at a rate approximately ten to fourteen times faster than a roadheader™bout 70 m per week for the TBM vs. 5 m per week for a roadheader. In addition, the final tunnels have a smooth profile and are segment-lined, requiring minimal upkeep during the planned 40-year life of the mine. “In the coal mining community, and certainly in Queensland, companies are aware of the Grosvenor project and how it has set a benchmark for underground access drift construction,” said Glen Maynard, Robbins Field Service Site Supervisor at Grosvenor.
The machine’s Crossover capabilities enabled it to operate in both hard rock and mixed ground. In addition, the TBM was required to operate during gaseous conditions. The unique TBM design included a cutterhead capable of interchanging hard rock and soft ground cutting tools, a two-stage center-mounted screw conveyor, a “quick removal” shield system, and flame-proof machine components due to the possibility of methane gas in the underground environment.
The TBM was optimized for hard rock and mixed ground excavation in geology ranging from soft clay and soil to sandstone and basalt. The two-stage screw conveyor worked in both ground conditions to draw muck from the tunnel face. Two sets of shields were built for the TBM’s “Quick Removal” system, and were detached from the machine at the end of each blind tunnel to be left in the ground for constant support, a requirement in Australian tunnels. The inner core components of the TBM were then retracted out of the segment-lined tunnels on specially designed transport dollies.
The machine began boring the conveyor tunnel in December 2013, and after completion in May 2014 was successfully retracted and transported to the second tunnel site. The machine was then re-commissioned for the people and equipment tunnel in November 2014 with a new set of shields. Once excavation commenced, boring was completed in 88 days at an average of 10.9 m per day, with a best day of 25.2 m. The bore itself was similar to the first, with few challenges encountered other than elevated methane gas levels that required several temporary stoppages in order to safely remove the gas from the tunnel. “The machine performed very well and had high reliability. The cutting tools, in particular the knife edge bits, were exceptional. The bits were required for most of the drive and one complete set lasted 650 meters,” said Maynard.
The team is now preparing the machine for its final retraction and roll-out, and it will be on the surface in less than two months. The TBM will then be stored onsite for future Anglo American mining projects.
Once the longwall mine is operational in 2016, Grosvenor is expected to produce five million tonnes of coal per year over the next 26 years.
Robbins teams up to bring Embattled TBM back to Life
The News In Brief:
- Breaking through on January 28, 2015, the rebuilt EPB at NYC’s Harbor Siphons tunnel overcame obstacles including flooding, extensive rebuild work, and difficult ground.
- The CAT-manufactured machine was fully submerged by Superstorm Sandy in October 2012 and became severely corroded by saltwater.
- Contractor Tully/OHL USA JV hired Robbins to rebuild and refurbish the machine, including all electrical components and an all-new PLC.
- The Robbins rebuild took four months and the machine was re-launched in April 2014.
- Robbins remained onsite to assist in continuing challenges including high water pressure and glacial geology.
- Despite the gamut of obstacles thrown at the machine, crews were able to achieve up to 30.48 m per day and 25 rings in 24 hours.
On January 28, 2015, about 35 m (115 ft) below New York Bay, a celebration was underway. Workers from the local tunnelers union in New York City, USA, known as the Sandhogs, completed the last meters of tunnel alongside workers for subcontractor Tully/OHL and Robbins field service. The team had many reasons to celebrate””not only had their TBM just completed a much-needed undersea tunnel, but it had also done so after a near-catastrophic natural disaster, extensive rebuild and geologic complications.
The New York City Harbor Siphons Project began simply enough””the 2.9 km (1.8 mi) long tunnel between Brooklyn and Staten Island was designed to replace two existing shallow water lines below the bay. The project, managed by the New York City Economic Development Corporation (NYCEDC), replaces the lines with the deeper siphon in order to make way for a larger project””the dredging of the Anchorage Channel. The channel (part of New York Bay) is an important waterway for shipping, and its dredging will allow for mega ships carrying large cargo loads to pass through.
Tully/OHL USA JV procured a 3.8 m (12.5 ft) diameter EPB TBM from Caterpillar in 2012. The TBM, dubbed “Pat”, was designed to drive through highly variable clays, sands, weathered rock and boulders. It was launched from the 35 m (115 ft) deep Staten Island shaft, boring towards the 40 m (131 ft) deep Brooklyn shaft, in August 2012.
In October 2012, the unexpected happened: a massive hurricane, dubbed Superstorm Sandy, barreled down on the U.S. East Coast with winds up to 145 kph (90 mph). Extreme flooding at the waterfront jobsite in Staten Island overtopped protective concrete barriers that had been designed three feet above the 100-year flood level. Seawater rushed into the tunnel and the nearly 113 m (370 ft) long machine was entirely submerged only 460 m (1,500 ft) into its drive. “Obviously this was our biggest challenge,” said Luis Alonso, Tunnel Manager for OHL. “After that, not many people thought we would be able to finish this tunnel.”
After floodwaters began to recede, OHL set about determining the extent of damage on the machine. The TBM was severely corroded by saltwater and sat idle until July 2013. During that time, CAT announced its impending closure of its TBM business, and the contractor looked to other manufacturers. “OHL was always determined to finish this project. After studying other options, we decided to proceed with the full refurbishment of the TBM with the help of The Robbins Company. The whole crew worked together to achieve that goal,” said Alonso.
Robbins coordinated the effort to replace corroded hydraulic components and all new electrical systems in mid-December 2013. Electrical systems had to be reverse-engineered, while the PLC had to be entirely redesigned. The refurbishment also centered on removing the rear eleven gantries and belt conveyor to be cleaned, evaluated and repaired. The rebuild took about four months, much of it done in the tunnel under water pressure, and crews were able to return to mining on April 14, 2014.
To ensure that the project stayed on the incline to success, Robbins Field Service personnel remained onsite to support ongoing maintenance of the TBM. With their help, machine performance steadily increased, eventually reaching rates as high as 30.48 m (100 ft) per day and as much as 25 rings in 24 hours in August 2014.
As excavation picked up, ground conditions changed from marine sediments (clay, silt and sand) to glacial geology with sand, exceptionally hard boulders, and excessive water ingress, resulting in slow propulsion rates. “The TBM needed more thrust and we decided to implement four additional auxiliary cylinders. Robbins field service helped in developing the size, features and location of the cylinders, which were eventually placed in the lower quadrant of the propulsion system,” said Alonso. With the new system crews were able to re-establish forward progress. The constant hurdles continued into early October when a hyperbaric intervention at 4 bar of pressure was required to change the cutting tools in a pocket of glacial soils. Despite the new obstacles, the crew was able to steadily increase the rate of excavation to 5 to 7 rings per day. “This tunnel is an important part of a larger project, and we are proud to be doing what we do every day, dealing with troubles as they come up, until we reach the end of the drive,” said Alonso. Now that tunneling is complete, the stationary and tail shields will be buried at the exit shaft entrance, with the cutterhead and back-up being removed.