Project Categories: Single Shield TBM

Delaware Aqueduct Repair

Single Shield TBM will bore through Difficult Conditions to fix the World’s Longest Continuous Tunnel

Project Overview

At 137 km (85 mi) long, the Delaware Aqueduct is cited in the Guinness Book of World Records as the world’s longest continuous tunnel. On any given day, it supplies 50-60% of New York City’s drinking water—a metropolis of 8.5 million people—in addition to a further 1 million that live north of the city. It is the largest such water supply tunnel in the United States. In the 1990’s, the New York City Department of Environmental Protection (NYCDEP) discovered that a section of the aqueduct below the Hudson River was leaking 75 million liters of water per day.

The NYCDEP took the decision to repair the tunnel in the largest such project to take place in the 175-year history of New York’s water supply system. A key component of the plan is a bypass tunnel that will connect up with structurally sound portions of the aqueduct and run deep below the Hudson for 3.8 km (2.5 mi). Notably, the tunnel will be bored while the aqueduct is still in service—only after excavation of the bypass will the flow be switched off to allow for the new tunnel to be connected to the existing tunnel. That shutdown is expected to last for five to eight months.

Geology

At 183 m (600 ft) below the riverbed of the Hudson, the bypass tunnel in faulted, crumbly limestone will be subject to water inflows at high pressures of up to 20 bar. A specialized 6.8 m (22.3 ft) diameter Single Shield TBM, manufactured by Robbins for JV contractor Kiewit-Shea Constructors (KSC), will bore the tunnel using components aimed at enabling efficient excavation in the difficult geological conditions.

Machine Design

The machine was designed with Difficult Ground Solutions (DGS) features for the unique conditions.

Water Inflow Control Features
Due to the 20 bar static water pressure expected on the project, a new main bearing sealing system was engineered for the project and is comprised of multiple rows of traditional lip type seals and emergency inflatable seals. In the event of a sudden inrush of high-pressure water, the TBM was designed to be quickly sealed. Knife gates over the muck chute are closed, followed by retraction of the conveyor frame and the belting from the cutting chamber. The bulkhead sealing plate is retracted and finally the stabilizer doors are closed.

Drilling & Grouting Systems
he machine is equipped with two drills in the shields for drilling through the head in 16 different positions and a third drill on the erector to drill through the shields in an additional 14 positions. Drilling and pre-excavation grouting will be a routine job to control and minimize water inflows. In addition, water-powered, high pressure down-the-hole-hammers will allow for drilling 60 to 100 m ahead of the machine at pressures up to 20 bar if necessary.

Pressure-Compensating Disc Cutters
The NYCDEP required that the TBM be capable of withstanding 30 bar of hydrostatic pressure. As such, the use of pressure compensated disc cutters became a necessity. Their unique design incorporates a pressure equalization system to keep water out and protect their bearings when the pressure is high.

Site Preparations

Two massive shafts were constructed—launch shaft 5B in Newburgh, New York, and a retrieval shaft in Wappinger on the other side of the Hudson. The shafts were constructed by drill and blast with concrete lining installed every 30 m (100 ft). Their construction was completed in March 2016, resulting in a 270 m (885 ft) deep, 9 m (30 ft) diameter shaft at Newburgh and a 197 m (646 ft) deep shaft at Wappinger.

The TBM will be launched from a bell-out chamber with a 12 m high ceiling currently under construction. The Newburgh shaft features a complex logistical setup including an elaborate hoisting system designed to service the shaft. The hoisting system will provide a lifting capacity of up to 90 metric tons to be used during TBM assembly.

Robbins worked closely with KSC to ensure that TBM components were designed and sized so all parts were less than 90 metric tons and could be lifted with the contractor’s hoist system to fit down the narrow, deep shaft window. A factory acceptance test was held in February 2017 After being shipped to the site, the TBM was assembled on a moving cradle at the bottom of the shaft, and then moved to the tunnel face.

In August 2019, The NYCDEP completed excavation of the Delaware Aqueduct Bypass Tunnel, a significant milestone in the USD $1 billion effort to repair leaks in the longest tunnel in the world. The TBM broke through a wall of shale bedrock nearly 700 feet (210 m) below the surface. Excavation of the tunnel was completed on budget and ahead of schedule.


Bahce-Nurdag High Speed Rail Tunnels

Robust Single Shield Navigates Turkey’s Hardest Rock

Project Overview

Gaziantep province, in Southeastern Turkey, is an important center of agriculture and trade divided into nine districts. With a population of nearly 1.7 million, the province is overhauling its public transportation with a rail line between the town of Bahçe and the Nurdağı district.  The Bahce-Nurdag Railway Tunnel will consist of two parallel 10.1 km (6.3 mi) tunnels, excavated by both drill and blast (2.9 km/1.8 mi) and TBM (7.2 km/4.5 mi).

Geology

The complex geology of the region is affected by the East Anatolian Fault zone, making ground conditions unpredictable. Mixed ground conditions prevail on the project, and range from interbedded sandstone, quartzite, and mudstone to highly weathered shale and dolomitic limestone.  High water ingress is predicted with several springs directly overhead.

Machine Design


The customized Single Shield TBM was designed with Difficult Ground Solutions (DGS).  Closure gates and an emergency sealing system effectively seal off high-pressure inrushes of water. The system reduces or eliminates the amount of mud or water that can pass through the machine and gives the crew time to safely grout off the water inflows.  During such an event the machine would be stopped until water inflows are reduced to the point that the TBM could begin excavation once again.

Onsite Assembly & Excavation

The Single Shield TBM was assembled at the jobsite using Onsite First Time Assembly (OFTA). The jobsite location about 20 miles (32 km) from the Syrian border complicated shipping of some parts but the assembly was completed and a launch ceremony held in January 2016.

The TBM encountered a very high strength rock mass—perhaps the highest strengths yet encountered in Turkey. Samples of meta-sandstone and meta-mudstone have tested at 223 Mpa UCS.

Breakthrough

On July 24, 2020 the first TBM-driven portion of tunneling was completed. The 8.9 km (5.5 mi) long tunnel that was excavated had some of the hardest and most abrasive rock encountered in Turkey. The TBM achieved up to 456 m (1,500 ft) per month, a result achieved with the help of a Robbins Continuous Conveyor System for muck removal.


Dulles Airport Train System

Swift Single Shields Excavate Dulles Airport

Project Overview

With more than 27 million passengers a year, the Dulles International Airport is one of the busiest hubs in the country. The Metropolitan Washington Airports Authority, project owner, created a scheme to maximize transportation efficiency at the airport via an extensive subway system. The new rail line, called the Airport Train System (ATS), was designed to eliminate the previous system of rubber-tired surface vehicles, which added to airport congestion. The USD $1.2 billion project includes a fleet of 29 rail cars capable of traveling up to 68 km/hr (42 mph) between stations.

While excavated using a variety of methods, a 560 m section needed to be TBM-driven due to the location of an active concourse directly overhead. The Atkinson/Clark/Shea JV, contractor for the twin tunnels, awarded a complete contract to Robbins in 2004for two 6.4 m (21.1 ft) diameter TBMs, back-up systems, cutters, and spare parts.

Geology

The tunnel passed through mudstone, sandstone and siltstone geology from 32 to 48 MPa (4,700 to 7,000 psi) UCS. Conditions in the tunnel required immediate grouting at the tail shield to limit settlement.

TBMs

The owner specified Single Shield TBMs due to the short tunnel lengths, tunnel lining requirements, and immediate grouting requirements. Robbins refurbished the Single Shield TBMs, which were originally built in 1985 for the Taipei Metro Subway. Each machine received a new cutterhead, back-up system, thrust controls, and segment erector.

The machines were fitted with 15″ diameter disc cutters to bore in relatively soft rock. The back-up system was designed as an open gantry system for single-track muck cars.

Tunnel Excavation

Each of the TBMs bored two tunnel drives, 460 m and 100 m (1,500 ft and 335 ft) in length. The TBMs bored the first 460 m (1,500 ft) section and were then walked through the 180 m (600 ft) long Concourse B station, excavated by cut and cover, to their second heading. While the TBMs bored, precast concrete segments were erected within the TBM tail shield to form the tunnel lining. Both TBMs had to maneuver through sharp turns with radii of 125 m (410 ft) as they approached the Main Terminal.

The machines broke through in September 2006. Many other methods including the New Austrian Tunneling (NATM) method and digger shields were used on the project as well. Phase 1 is slated for completion in 2009 and will provide rail service from both Concourse B and Concourse C to the main Terminal.


Theun Hinboun Expansion Project

Project Overview

Single Shield TBM for the Laos Project

The Theun Hinboun Expansion Project is a hydroelectric project that requires a 5.5 km (3.4 mi) headrace tunnel bored by a Robbins Single Shield TBM – the first instance of TBM-driven tunneling in the country of Laos. Located on the banks of the Nam Theun River, the project consists of a new station, dam, and headrace tunnel which will add electricity supplies to Laos and neighboring Thailand by 2012. The USD $270 million project will address the power needs of the two countries by adding an additional 280 MW annual generating capacity.   The original plant, built by Recchi-CMC JV between 1995 and 1998, already produces 220 MW annually. Power will be shared, with approximately 220 MW going to Thailand and 60 MW to the Laotian national power company, Electricite du Laos (EDL). The project also promises to improve the supply of electricity in Laos by extending the 115 kV transmission grid to the project area and increasing power supply to the existing grid.

Single Shield TBM Design

On December 22, 2008, CMC di Ravenna signed a contract with Robbins to provide a 7.6 m (15.1 ft) diameter Single Shield TBM. The TBM was assembled at Robbins’ Solon manufacturing facility in Ohio and shipped to the jobsite along the Nam Theun River. CMC di Ravenna chose the Robbins Single Shield for its short shield length, based on the geology and the need for continuous tunnel lining.

The Robbins TBM was designed to accommodate moderate squeezing ground conditions. Ground along the tunnel alignment consisted of alternating strata of sandstone, siltstone, and mudstone. An articulating cutterhead with overcutters allowed the machine to excavate 100 mm  (4 in) beyond the nominal tunnel diameter. To support the ground and provide final lining, 280 mm (11 in) thick, pre-cast concrete segments were used in a 5+1 arrangement, making a finished tunnel diameter of 6.9 m (22.6 ft).

TBM Excavation

During excavation, the Robbins Single Shield TBM averaged 19 m (62 ft) per day, with a peak advance rate of 37 m (121 ft) in one day.  Ground conditions consisted of fair to good rock for 95% of the tunnel length, with some sections of poorer rock quality.

Challenging conditions included an anticipated 15 m (50 ft) wide fault zone at about the 4,700 m (2.9 mi) mark with flowing water.  The crew was able to drill a borehole and use expanding foam to consolidate the ground, allowing boring to continue.  The machine broke through on schedule, on November 21, 2010.


El túnel de Pajares, lote 4

Project Overview

The Pajares Lot 4 tunnel is part of Spain’s AVE high-speed rail link. The entire 49.5 km (30.8 mi) long tunnel connects Asturias to the Madrid-Valladolid high-speed link. The route was divided into four lots, with two tunnels for traveling both east and west.

Project owner, Administrador de Infraestructuras Ferroviarias (ADIF), awarded the construction contract for Lot 4, a 10.5 km long section of tunnel, to a joint venture of Constructora Hispanica, Azvi, Brues y Fernandez and Copcisa. The joint venture chose a 10 m (32.8 ft) diameter Single Shield TBM to bore the tunnel. The TBM was designed by Robbins and built by Mitsubishi Heavy Industries. The machine was pre-assembled at a shop in Spain and final assembly was completed onsite.

Geology

The machine began boring in August 2006 through sandstone, shale, limestone, molasse, and volcanic rocks with Unconfined Compressive Strengths (UCS) of 40 to 90 Mpa (6-13 ksi). Robbins’ Single Shield design allowed the machine to cope with this fractured and varied rock. The machine could also erect 500 mm (19.7 in) thick pre-cast concrete segments to support the tunnel walls in troublesome geology.

TBM and Tunnel Excavation

Robbins Single Shield TBM launched at PajaresThe TBM featured 17 inch (432 mm) cutters and was powered by 5,180 kW (6,946 hp) to generate a maximum cutterhead thrust of 16,814 kN (3,780,000 lb). The back-up system for the machine consisted of open gantries.  Tunnel excavation was completed in July 2009.


Proyecto de irrigación en la isla de La Reunión

Descripción del proyecto

El proyecto de irrigación de la isla de la Reunión se sitúa en dicho territorio francés en el océano Índico, consistiendo en un conjunto de túneles para el regadío de las plantaciones de caña de azúcar, así como para proporcionar agua a los habitantes de la zona oeste de la isla. Dichos túneles transportan el agua desde tres manantiales situados en la zona este de la isla, rica en este elemento, hasta los mucho más áridos territorios del oeste. Entre las organizaciones que han financiado el proyecto está la Unión Europea, el Gobierno Francés, el Departamento de La Reunión y la autoridad de la región de La Reunión.

La constructora SOGEA adjudicó a Robbins en 1990 el contrato de suministro de tuneladora. Robbins construyó una TBM de escudo simple de 4,3 m de diámetro para la perforación de los túneles I y II. El túnel I tiene como objetivo transportar las aguas provenientes del túnel III, así como el agua fluvial de la Rivière de Galets. Esta agua recorre 8,6 km hasta un embalse al oeste de la isla. El túnel II es una galería de solamente 2,4 km que trasvasa , vía sifón, el agua del túnel I por debajo de la Rivière de Galets.

Geología

La geología de los tres túneles constaba fundamentalmente de basaltos con olivinos. Las fallas que la traza atravesaba habían creado zonas muy fracturadas en bloques en las que se encontraban arcillas y lutitas. En estas zonas se produjeron frecuentes avenidas de agua y otras alteraciones geológicas.

TBM

Robbins diseñó la tuneladora de escudo simple para abordar el desafío especial de perforar roca abrasiva contra avenidas de agua en ambos túneles. La cabeza de corte de la máquina incluía cinco cangilones de recogida de escombro y 29 cortadores de 17” con perfil reducido y desmontables desde el interior de la máquina para mayor seguridad del personal.

La cabeza de corte iba accionada por seis motores de 160 kW cada uno, que proporcionaban un par de más de 1297547 Nm. La cabeza de corte, de dos velocidades de giro y articulada, facilitaba el control de la dirección de perforación así como la estabilidad en terrenos fracturados. Robbins equipó también a la máquina con sistemas de bombeo y sellado de la cabeza de corte y escudo, preparando la máquina para acometer la perforación del basalto en condiciones de ingreso masivo de agua.

El sistema de ventilación de la TBM incluía un ventilador de 900 mm de diámetro, tubería de aire, unidad de aire acondicionado y sistema de acumulador de tubería en “cassette”, todo ello montado en el back-up de la máquina.

Perforación del túnel

La tuneladora se enfrentó a los primeros problemas geológicos al inicio del túnel I. Durante los primeros 500 m se atravesaron zonas de detritus volcánico duro, agua y roca fracturada en bloques. La tuneladora atravesó dos zonas de roca muy mala con entradas de agua al túnel de unos 45 l/s. El personal del contratista y los técnicos de servicio de Robbins idearon varias modificaciones a la máquina para mejorar su rendimiento en estas condiciones, como el desmontaje del cortador prolongable para permitir la instalación de un sexto cangilón de recogida de escombro, lo que en adelante facilitó la limpieza de la cabeza de corte aumentando la eficacia de la perforación.

El basalto con olivino, de carácter blando pero de muy alta abrasividad, causó muchos problemas de desgaste de las carcasas de los cortadores de la máquina. El problema lo resolvió parcialmente el personal de obra endureciendo la superficie de dichas carcasas. En las condiciones más extremas de abrasividad, la vida de los discos de corte se situaba entre las 300 h de los cortadores centrales a las 50 de los cortadores en posición de gálibo.