White Papers

Tunneling through 48 Fault Zones and High Water Pressures on Turkey’s Gerede Water Transmission Tunnel

The December 2018 breakthrough of a 5.5 m diameter hybrid-type Single Shield/EPB TBM at the Gerede Water Transmission Tunnel in Central Turkey was a feat of modern construction. The 9 km leg was the final section of the 31.6 km long water supply line bored through what is widely considered to be Turkey’s most challenging geology. The project was originally started with the contractor selecting three Double Shield machines, which were procured and supplied without Robbins involvement. When two of the machines became stuck and were unable to continue, the solution of the hybrid-type TBM was developed to complete the rest of the tunnel. The TBM was assembled and launched more than 7 km from the tunnel portal and successfully navigated 48 fault zones as well as hydrostatic pressures up to 26 bar.

 

  Download File