白皮书论文

Overcoming Extreme Tunneling Conditions in Vietnam’s Longest Tunnel

Vietnam’s Thuong Kon Tum Hydroelectric project is a 17.4 km headrace tunnel that will be the country’s longest once complete. A section of the tunnel was excavated by a 4.5 m diameter Main Beam TBM in granitic rock up to 250 MPa UCS. Started in 2012, the project’s original contractor left due to non-satisfactory performance. In 2016, the contract to refurbish the TBM and excavate the remaining 10.45 km of tunnel was awarded to a joint venture of Robbins and a local contractor. Robbins was fully responsible for the TBM operation, including supplying operational crews. The crew overcame massive granitic rock, fault zones gushing water at 600 l/s, and difficult conditions. In under two years, the TBM advanced from a standstill at 15 percent project completion to 85 percent complete. This paper addresses the refurbishment of the TBM in the tunnel, the work to streamline operation, and challenges faced.

 

  Download File